Memorial Stadium Centennial Project

Project Overview

Designed to preserve the stadium’s tradition-rich elements while embracing a vibrant future for Mizzou, the $250 million Memorial Stadium Centennial Project will enhance the fan experience by further enclosing the north end of the stadium and adding a variety of new premium seating options along the north edge of the stadium along with other upgrades throughout the facility.

Square Footage:

191,100 GSF

Budget:

$250,000,000

Timeline:

  • Bid Due Date: April 3, 2025 at 1:30 PM CDT
  • Construction Start Date: November 30, 2024
  • Substantial Completion Date: October 2026

Awarded To:

DLR Group

Architect(s):

DLR Group

Closures & Maps:

View the Construction Impact Map

Project Photos:

Aerial view of proposed Memorial Stadium Centennial Project, showing the football field sitting alongside Stadium Blvd.

Aerial view of proposed Memorial Stadium Centennial Project, showing the football field sitting alongside Stadium Blvd.

An endzone lounge full of fans, at the Memorial Stadium.

An endzone lounge full of fans, at the Memorial Stadium.

The proposed Rock M Club.

The proposed Rock M Club.

Additional Resources: